Report guide

Arboricultural Impact Assessment (AIA)

An Arboricultural Impact Assessment tests a specific design — buildings, driveways, services and excavation — against each retained tree's Notional Root Zone (NRZ) and Structural Root Zone (SRZ), quantifying encroachment and recommending mitigation.

What an AIA typically includes

  • NRZ (from DSH) and SRZ (from DARB) calculations to AS 4970:2025 for every tree affected by the proposal.
  • Overlay of the design footprint on each zone to identify and measure encroachment.
  • Classification of encroachment as minor (up to 10% of the NRZ area), moderate (more than 10% and up to 20%) or major (more than 20%, or any SRZ intrusion), with compensating TPZ area where required.
  • The proposed Tree Protection Zone — the area to be physically fenced off — for each retained tree.
  • Recommendations such as root investigation, engineering solutions (e.g. pier and beam footings) or redesign.

When you need one

Most councils require an AIA as part of a development application whenever proposed works are within, or close to, a tree's NRZ. It's typically prepared once a concept design exists, following an earlier Preliminary Arborist Report.

Calculating encroachment

Encroachment area is the portion of a tree's NRZ circle that a design footprint covers. Use the Encroachment Zone Calculator to draw the footprint to scale and classify it under the AS 4970:2025 minor, moderate and major bands before committing to a design.

Related tools and guides

Get updates as EasyTrees develops

EasyTrees is building offline-ready field data collection and templated report generation for arborists. Join the early-access list to follow progress and help shape the workflow.

Product updates and research invitations only. Unsubscribe at any time.